Special to North Carolina Construction News
North Carolina’s new state budget sets aside $1 million for landslide mapping in Western North Carolina, but lawmakers limited the work to risks facing roads, bridges, power substations and other public facilities. The money cannot be used to map risks to private homes or residential neighborhoods. That distinction matters for contractors who build on the region’s steep residential slopes.
Budget Limits Mapping to Critical Infrastructure
The landslide line belongs to a Helene recovery package topping $700 million in the fiscal year 2026-27 budget, which Gov. Josh Stein signed in July of 2026. The money is aimed at landslide risks near critical infrastructure, including highways and public facilities. Mapping risks to homes or residential neighborhoods falls outside the scope of the funding.
Stein tied the mapping money to public safety when discussing the budget. “If we know where these risks are, we can do a better job keeping people informed and keeping them safe,” Stein said.
Steep slopes and saturated soil leave mountain terrain vulnerable to slides during heavy rain, and those slides often reach the roads, bridges and utility lines below.
State road repairs show the scale of slope work on public assets. The N.C. Department of Transportation awarded a $32 million contract to rebuild a 1.1-mile section of U.S. 176 using soil-nail walls, pile-panel walls and grouted rock embankments.
Mapping Funding Falls Short of Earlier Requests
This year’s North Carolina landslide mapping funding is smaller than state officials sought. Stein’s Helene budget recommendation in March sought $1.4 million in funding for the Department of Environmental Quality to continue its landslide hazard mapping and warning system.
State lawmakers set aside $3 million in 2025 for hazard mapping in storm-damaged counties. That sum is roughly half the $6.1 million a governor’s recovery advisory panel proposed to extend mapping to 15 counties and refresh nine existing county maps. Funding for the program was cut in 2011 and partly restored in 2017.
The funding history underscores why the new limits matter beyond public infrastructure. While state funds are directed toward roads and other public facilities, contractors working on private residential sites may still face slope and drainage risks that fall outside the mapping effort.
Gaps in landslide mapping matter on residential lots, where site work itself can add risk. Construction on steep slopes can alter drainage patterns and increase the risk of landslides, according to geohazard mitigation firm GeoStabilization International.
Asheville and Buncombe County Fund Separate Landslide Studies
Cities and counties are paying for landslide engineering on their own. In Asheville, the city council approved three projects totaling roughly $11 million for landslide design and engineering work. The city expects the Federal Emergency Management Agency to cover the bulk of the costs.
The council unanimously approved three resolutions for the work on June 23. ECS Southeast LLC will handle two of the projects, and Catawba Valley Engineering and Testing PC will oversee the third. The city had not said when work would begin or how long it would last.
Buncombe County commissioners in June hired ECS Southeast for $1.83 million to evaluate ways to reduce slide risk around Fairview’s Garren Creek area, where 13 people died in Helene-driven slides in Garren Creek and Craigtown. It ranks as the county’s second of three planned mitigation projects, and FEMA and N.C. Emergency Management are paying for it through Public Assistance funds.
Engineering studies like these generally weigh slope stability, drainage and the cost of possible fixes before crews begin any repair work.
State Geologists Point to Existing Hazard Maps
The North Carolina Geological Survey already maintains an online landslide hazard data viewer for the mountain region. Its layers mark slide starting points, outline the rough footprint of each slope movement and show where earth and debris came to rest.
David Korte, who leads the state’s landslide mapping program at the N.C. Department of Environmental Quality, said at a January meeting of the governor’s recovery panel that he hopes new maps will help emergency managers safeguard critical infrastructure and plan evacuation routes.
He added that the maps will identify some sites needing attention before homes go up, flagging certain lots where the ground may need work, and in some cases clearly should get it, before anyone builds a house there.
Some mountain-area realty firms require staff to check the state map before disclosing landslide risk on home sales, Korte said.
Lawmakers and Local Rules Weigh Steep-Slope Development
State Sen. Ralph Hise, a Republican from Mitchell County, pressed Korte at that meeting on whether hazard maps might hinder development in the mountains.
Hise said residents worry that if mapping labels whole counties as hazard areas, development there could stop altogether.
Local zoning also applies. Buncombe County added steep slope development restrictions to its zoning ordinance in 2010, a year after adopting ridge protection. Asheville and the county also offer a web-based slope calculator that lets developers check the grade of any Buncombe County parcel.
Local Engineering Work Awaits Next Steps
Asheville had not set start dates for its three landslide engineering projects when the council approved them, and Buncombe County has one more mitigation project planned after Garren Creek. The state’s $1 million mapping effort targets highways, bridges, substations and other public facilities, while residential parcels remain outside its scope.